Church-Throup Road Roundabout Approaching Substantial Completion:
UPDATE – Monday, April 15, 2024, 12:34 pm: The paving is scheduled for Wednesday, April 17 and Thursday, April 18. Closures are anticipated from 9 AM to 5 PM.
Top Lift Paving Scheduled for April 16 and 17
Friday, April 12, 2024 – Progress continues with the Church-Throup Roundabout Project with less than four days of road closures expected for the duration of the project, including two next week.
Early rainfall this morning delayed the pouring of the top lift today; however, with sunny days ahead, this milestone is set to be realized on Wednesday, April 16 and Thursday, April 17.
In response to public feedback, construction crews will adjust their schedule to mobilize later in the morning. This action aims to mitigate disruptions during school drop-off hours, thereby (in at least a small capacity) lessening some of the inconvenience to residents and commuters. When the road is closed, hours of work are expected to be approximately 9 am to 5 pm.
“We are in the home stretch!” says Project Manager, Sue Basset with Hazelwood Construction. “We currently expect two more days of closures following this milestone for the remainder of the project.”
The community’s patience and understanding during these essential infrastructure improvements are appreciated.
Follow the implementation of the Transportation Master Plan at letstalk.sooke.ca/tmp.
Learn more about traffic advisories:
Link: Church-Throup Road Roundabout – Top Lift Paving Scheduled for April 16 and 17 (sooke.ca)